| General Information | |
|---|---|
| Type | Hyperscale |
| Status | Permitted |
| Address | 85 SHARPS ROAD TULLAMARINE 3043 |
| Developer(s) | AirTrunk |
| Permit Pathway | Development Facilitation Program (DFP) |
| Local Council | Brimbank City Council |
| Build Details | |
| Cost | $973.97 million |
| Area | 45,578 m2 |
| Power draw | 354MW |
| Backup | Unknown |
| Community Opposition | |
| Community groups | |
Summary
Ownership history
The site was purchased by global real estate firm Hines from Honda Australia on 31 August 2022, with Honda's warehouse tenancy set to vacate in early 2024 [1]. AirTrunk announced on 24 December 2025 that it had acquired the site from Hines for $187 million, to build its second Melbourne campus (MEL2), reported at the time to be part of a broader ~$5bn AI infrastructure push [2]. AirTrunk's own announcement described MEL2 as a new hyperscale campus with over 354MW of planned capacity [3].
Approval pathway
The original application was lodged by "EMKC3 Pty Ltd" via the Development Facilitation Program (DFP) on 20 December 2024, following a pre-application enquiry that was lodged on 19 September 2024. Public notice ran from 4 February 2025, with no objections received from adjoining owners/occupiers (including Melbourne Airport) [4]. DTP approved the application on 28 March 2025 [5], with the formal permit document issued 11 April 2025.
A separate VicSmart application (P47/2025) for early "clearing, excavation and trenching" works at the site was lodged with Brimbank City Council on 14 February 2025 by an unnamed applicant and approved on 27 February 2025 [6]. This was consistent with the DTP officer report's note that the applicant held a VicSmart permit enabling early works ahead of full plan endorsement.
An amendment application (PA2403452-1) was lodged by Angle Planning on 10 April 2026, seeking to reduce the number of data halls from 8 to 5 and relocate plant equipment from the roof [7]. DTP approved the amendment on 26 June 2026 [8].