Resources:Centuria Clayton
| General Information | |
|---|---|
| Type | Colocation |
| Status | Suspended |
| Address | 1816-1832 DANDENONG ROAD CLAYTON 3168 |
| Developer(s) | Centuria |
| Permit Pathway | Council Application for Planning Permit |
| Local Council | Monash City Council |
| Build Details | |
| Cost | TBA |
| Area | 10,390 m2 |
| Power draw | 40MW |
| Backup | 24 x 3.1 MW generators; 468kL of diesel stored on site |
| Community Opposition | |
| Community groups | |
Summary
Centuria purchased the Telstra in 2020, in a long-term sale-leaseback deal. The 27,105 sqm (291756 sq ft) site, at 1822 Dandenong Road, contains two data centres totalling around 12MW, one of which was opened in 2014. As part of its Q1 FY2026 results, Centuria said it was "seizing the opportunity" to develop a second data centre adjacent to the existing Telstra-occupied data center in Clayton. "Telstra has agreed to partially surrender underutilized land, providing an opportunity for a second data center of up to 40MW" the company said. [1]
On 25 February 2026, an application was lodged with Monash City Council (TPA/57779) for the construction of a four storey data centre. On 29 September, refused to issue the permit. As per w.media, the refusal "was driven principally by concerns about the scale and intensity of the expansion, its electricity requirements and potential impacts on surrounding residents, alongside uncertainty about how the project fits into Victoria’s rapidly changing data centre policy." [2]