Resources:HiQ Eco-Hub
From Data Centre Moratorium Wiki
| General Information | |
|---|---|
| Type | Mega campus |
| Status | Proposed |
| Address | 580 SUNBURY ROAD BULLA 3428 |
| Developer(s) | HiQ |
| Permit Pathway | Development Facilitation Program (DFP) |
| Local Council | Hume City Council |
| Build Details | |
| Cost | TBA |
| Area | TBA m2 |
| Power draw | 1GW (proposed) |
| Backup | TBA |
| Community Opposition | |
| Community groups | |
Summary
Sunbury Eco-Hub is a project that was first announced by HiQ in August 2025 [1] after it had been issued a cap licence by Recycling Victoria. The license permits HiQ to process up to 750,000 tonnes of waste through a "waste-to-energy" facility [2].
In March 2026, HiQ released a brochure geared towards investors [3]. In it, HiQ details a plan for a "connected precinct" that includes:
- a 750,000 tonne-per-annum waste-to-energy (WtE) facility that will produce "at least 80 megawatts of electricity".
- a Battery Energy Storage System (BESS) that will provide "up to one gigawatt of storage capacity" and will be connected to nearby transmission lines.
- 100 hectares of industrial land
- over 50 hectares of residential land
- a hyperscale campus that will "provide one gigawatt of processing capacity"
According to the project page, technical assessments have been completed (2024 - 2026) and the project is currently in the community engagement period. Once the community engagement period ends, HiQ will likely submit an application to the Department of Transport and Planning through the Development Facilitation Program (DFP)[4].