Resources:NEXTDC G1

From Data Centre Moratorium - Wiki

General Information
Type Edge
Status Under construction
Address 148-158 O'Briens Road, Corio
Developer(s) NEXTDC
Permit Pathway Development Facilitation Program (DFP)
Local Council Greater Geelong City Council
Build Details
Cost $85 million
Area 40,060 m2
Power draw 4.4MW
Backup Unknown
Advocacy Resources
Community push back TBA
Resistance status TBA
Advocacy information TBA
Petition TBA
Community resources TBA


Summary

PA2503895

Overview

G1 will be NEXTDC's first data centre in Geelong. NEXTDC purchased the site for more than $16 million in 2024 [1], and has engaged Kapitol as the builder [2]. The facility is expected to be operational in the second half of 2027. A fast-tracked permit was granted via the Victorian Government's Development Facilitation Program PA2503895.

Noise

Preliminary acoustic advice (NDY/GHD, 22 August 2025) found predicted noise from mechanical plant and standby generators may, without mitigation, exceed EPA night-time limits at the nearest residential receivers south of the site. The permit requires a detailed Acoustic Environmental Impact Assessment confirming compliance with EPA Publication 1826.4 prior to commencement, with either quieter generators (≤106 dBA sound power) or a solid noise barrier recommended as mitigation options.

Build stages

Stage 1Under construction

One data hall, front-of-house office, loading facilities, utilities and car park landscaping. Approximately 3,377m² of site coverage.

Stage 2Planned

Additional data halls, expanded office/storage and further car parking. Total site coverage increases to approximately 7,312m².