Resources:NEXTDC M4

From Data Centre Moratorium Wiki

Update this data centre

General Information
Type Hyperscale
Status Permitted
Address 127 TODD ROAD PORT MELBOURNE 3207
Developer(s) NEXTDC
Permit Pathway Development Facilitation Program (DFP)
Local Council Melbourne City Council
Build Details
Cost $2 billion
Area 94,987 m2
Power draw 162MW
Backup 90 containerised diesel generators (3,570kL storage); ~900 tonnes of lithium-ion batteries
Community Opposition
Community groups No AI Data Centre in Port Melbourne


Summary

  • Approved by the Minister for Planning via the DFP (PA2504019, Clause 53.22). Permit issued 16 January 2026. No public notice and no third-party review rights.
  • The build will include a five-storey building, 40.5m high (47.5m to the top of roof plant), 94,987 sqm floor area, on a 5.8 ha site directly abutting Westgate Park. 106 trees will be removed (97 native) and there will be up to 180 staff and visitors on site when complete.
  • The noise assessment predicts 58 dB(A) at the 1 Wharf Rd education facility against a 59 dB(A) limit (1 dB margin). Westgate Park noise was assessed at the car park, not next to the site. The permit has no post-commissioning noise monitoring condition.
  • The stormwater plan increases discharge into the Westgate Park wetland by ~11%, and contradicts the sustainability plan on stormwater re-use tanks ("six" vs "none"). * The endorsed sustainability plan commits to no solar PV and no recycled water, despite NEXTDC's public claims of on-site solar, recycled wastewater cooling and waste heat recovery.

Sources for the above information were obtained via public inspection request to the Department of Transport and Planning (DTP):

  • DTP Officer Assessment Report PA2504019 (signed 16 Jan 2026): pp. 3–5, 12, 35–36
  • Planning Permit PA2504019 (16 Jan 2026): conditions 23–25
  • Endorsed Environmental Noise Assessment (Aurecon, Rev B, 30 Sep 2025): pp. 7, 11, 26–27, 30, 32
  • Endorsed Stormwater Management Plan (Innovis, 21 Oct 2025): pp. 4, 6
  • Endorsed Sustainability Management Plan (Aurecon, Rev 3, 5 Mar 2026): pp. 10, 20

Build stages