General Information
Type Hyperscale
Status Under construction
Address 411 PALMERS ROAD TRUGANINA 3029
Developer(s) STACK Infrastructure,Hickory
Permit Pathway Council Application for Planning Permit
Local Council Wyndham City Council
Build Details
Cost TBA
Area 21,000 m2
Power draw 252MW
Backup Not publicly disclosed
Community Opposition
Community groups


Summary

Permit Timeline

On 20 December 2024, Tract Consultants Pty Ltd lodged an application for a planning permit to Wyndham City Council (WYP14917/24). The planning permit was issued by council on 4 July 2025.

19 March 2025: Saville & Co lodged a building permit (Section 30) application to Wyndham City Council (2025P44312) to demolish "existing structures" on the site. The permit was issued by council on 30 July 2025.

17 September 2025: Saville & Co lodged a building permit (Section 30) application to Wyndham City Council (2025P45542) for pre-works (piling and inground services). The permit was issued by council on 15 September 2025 (???).

19 December 2025: Saville & Co lodged a building permit (Section 30) application to Wyndham City Council (2025P46088) for construction works: "Structural Ground & Level 1 Horizontal Slabs, including Architectural Concrete Profiles, Structural Ground to Level 5 Full Vertical Elements and Stairs.". The permit was issued by council on 16 December 2025 (???).

13 February: Head Transport For Victoria (Head Tfv) sends a referral for an application for a planning permit to Wyndham Council (MPA26/0049). The permit was issued by council on 27 April 2026.

19 February 2026: Neocheck Kinban Group lodged a building permit (Section 30) application to Wyndham City Council (e2026P55826) for "Construction of One (1) Substation, Six (6) Transformer Bunds & associated Fire Walls and Lightning Pole Construction of 6 x Transformer Bunds and Associated Fire Walls Only". The permit was issued by council on 11 February 2026 (???).

4 March 2026: Tract Consultants Pty Ltd lodged an application to amend a planning permit to Wyndham City Council (WYP14917/24.05). There are no details as to what what was amended. The permit was issued on 12 May 2026.

27 March 2026: Saville & Co lodged a building permit (Section 30) application to Wyndham City Council (2026P46518) for "fitout works for new data centre". The permit was issued by council on 12 March 2026 (???).

27 March 2026: Saville & Co lodged a building permit (Section 30) application to Wyndham City Council (2026P46519) for the "construction of a new substation". The permit was issued by council on 8 April 2026 (???).

14 May 2026: Saville & Co lodged a building permit (Section 30) application to Wyndham City Council (2026P46824) for above-ground services (electrical, mechanical, hydraulic, data halls) on levels 3, 4 and 5 of the data centre. The permit was issued by council on 30 April 2026 (???).

27 July 2026: Energy Solutions (Beon) lodged an "Council Report and Consent" application to Wyndham City Council (BDREPCON-2026/003137) for "construction on designated land or designated works". The application is currently under review by council.

Build stages

Stage 1 —

A single 252MW building on 5.6ha, offering 21,000sqm of technical area and 3,000sqm of office/storage space, served by a dedicated onsite 132kV substation with 300+MW gross capacity [1]. Address of 411 Palmers Road, Truganina per a Hickory project coordinator's listed work history [2], corroborated by an independent Wyndham City Council planning application (Section 72 amendment to plans) recorded at that address, 6 March 2026 [3]. No anchor tenant has been publicly disclosed.